To work out how much fill dirt you need, multiply the length, width and depth in feet and divide by 27 to get cubic yards, then add 10 to 20 percent if the dirt will be packed down. That is the whole calculation, but fill dirt has a habit of surprising people anyway. It swells when it is dug, shrinks when it is compacted and weighs more than most trailers can carry. This guide covers how to measure the space properly, how much extra to order, what a yard of dirt weighs and how to tell fill dirt from the soil you actually want to plant in.
The Quick Answer
- Cubic yards of fill dirt = length (ft) × width (ft) × depth (ft) ÷ 27.
- With the depth in inches: square feet × depth (in) ÷ 324.
- One cubic yard fills 324 square feet 1 inch deep, 81 square feet 4 inches deep or 27 square feet 1 foot deep.
- Add 10 to 20 percent for fill that will be compacted in layers.
- Dry fill dirt usually weighs about 1.1 to 1.3 tons per cubic yard, and wet clay weighs more.
If you already know the area, enter it below with the depth in inches. For odd shapes, the cubic yard calculator works out the area for you and adds the allowance you choose.
Fill Dirt, Topsoil or Structural Fill?
Fill dirt is subsoil: the mineral layer below the dark, crumbly topsoil, with little organic matter in it. That is exactly what makes it good for raising ground, because there is almost nothing in it to rot away and leave a dip. It is also what makes it poor for growing anything. Before you order, match the material to the job.
| Material | What it is | Use it for |
|---|---|---|
| Fill dirt | Subsoil with little organic matter, sometimes with stones or clay | Raising grade, filling holes and low spots, backfilling |
| Screened fill | Fill dirt sieved to remove rocks and debris | Fill that will sit under a thin layer of topsoil |
| Topsoil | The dark upper layer, rich in organic matter | The top 4 to 6 inches under a lawn or garden |
| Structural fill | Tested soil or crushed stone that compacts to a known strength | Under slabs, footings and driveways, as your engineer or local code requires |
A common money saver is to build up most of the height with fill dirt and finish with a few inches of topsoil, which our topsoil guide covers in detail. Under a building, a slab or a driveway, use the fill your engineer or local code calls for rather than ordinary fill dirt.
How to Measure Cubic Yards of Dirt
- Mark out the area and measure its length and width in feet. Split an L shape or a curve into rectangles and circles and measure each piece.
- Measure how deep the fill needs to be, from the current ground up to the finished level. On uneven ground, take several readings and average them.
- Turn the depth into feet by dividing inches by 12, so 6 inches is 0.5 ft.
- Multiply length × width × depth to get cubic feet, then divide by 27 for cubic yards.
- Add your compaction allowance and round up to the amount your supplier sells.
Measuring a low spot or a slope
Low areas are rarely the same depth everywhere. Run a string line between stakes at the finished height, pull it level, and measure the gap down to the ground at evenly spaced points. Say a dip 20 ft by 15 ft gives readings of 2, 5, 6, 4 and 3 inches. The average is 20 ÷ 5 = 4 inches, so the fill comes to 300 × 4 ÷ 324 = 3.70 cubic yards. On a large or steep area, more readings give a better average.
Measuring a round hole
For a round hole, such as the one left by a stump, the volume is 3.1416 × radius × radius × depth. A hole 4 ft across and 2 ft deep has a radius of 2 ft, so it holds 3.1416 × 2 × 2 × 2 = 25.13 cubic feet, and 25.13 ÷ 27 = 0.93 cubic yards. Holes are often wider at the top than the bottom, so measure the width halfway down for a fairer figure.
How Much Fill Dirt for Common Projects
Building up a garden area or a shed pad
Raising an area 30 ft by 20 ft by one foot takes 30 × 20 × 1 = 600 cubic feet, or 600 ÷ 27 = 22.22 cubic yards. Because the fill will be compacted in layers, add 15 percent: 22.22 × 1.15 = 25.55, so order 26 cubic yards. A shed on that pad still needs the base the shed maker specifies on top, usually gravel.
Backfilling behind a retaining wall
A wall 40 ft long and 3 ft high with a 2 ft wide strip to fill behind it takes 40 × 2 × 3 = 240 cubic feet, which is 240 ÷ 27 = 8.89 cubic yards. Most wall systems call for drainage gravel directly behind the blocks, with fill dirt beyond that, so follow the manufacturer's drawing and take the gravel out of the dirt total. Our gravel guide works out the stone.
Filling an old flower bed or a trench
A bed 12 ft by 4 ft that has to come up 8 inches to meet the lawn needs 48 × 8 ÷ 324 = 1.19 cubic yards. If it will be seeded, make the top 4 inches topsoil and only the rest fill dirt. For a trench, use the same sum with the trench length, width and depth.
Bank, Loose and Compacted Dirt
Dirt does not keep the same volume as it moves, and this is where most fill orders go wrong. Soil still in the ground is measured in bank cubic yards. Once it is dug, air gets in and it swells into more loose cubic yards, often 20 to 30 percent more. When it is spread and packed down, it settles into fewer compacted cubic yards. That is why a hole of 10 bank yards can fill a truck with 10 × 1.25 = 12.5 loose yards.
Loose dirt to order = finished volume × (1 + compaction allowance)
Example: 10 yd³ finished with 15% allowance → 10 × 1.15 = 11.5 yd³
How much extra to order
For fill that will be compacted in layers, many contractors add 10 to 20 percent. For dirt simply spread in a garden and left to settle, 5 to 10 percent is usually enough. Clay and wet soil settle more than sandy soil, so ask your supplier how much their fill compacts, and put that figure in the waste field of the calculator.
How Much Does a Yard of Dirt Weigh?
| Material | Tons per cubic yard | Pounds per cubic yard |
|---|---|---|
| Dry fill dirt | 1.1–1.3 | 2,200–2,600 |
| Topsoil | 1.1–1.3 | 2,200–2,600 |
| Wet clay | 1.5 or more | 3,000 or more |
Treat these as starting points, because moisture and stone content change the figure. The 3.70 yard low spot above weighs about 3.70 × 1.2 = 4.44 tons at a middle density. For any material, our guide to how many tons are in a cubic yard explains where the numbers come from.
How many yards of dirt are in a ton?
Divide one by the density. At 1.2 tons per yard, 1 ÷ 1.2 = 0.83 cubic yards per ton. Across the usual range, 1 ÷ 1.3 = 0.77 and 1 ÷ 1.1 = 0.91, so a ton of dirt fills a little under one cubic yard. The tons to cubic yards converter does this for any density your supplier quotes.
Hauling it yourself
A single cubic yard of dry fill weighs well over a ton, more than many pickups are rated to carry. Check the payload figure on the sticker inside the driver's door before loading, and split the job into trips or book a delivery if the numbers do not fit.
Ordering and Delivery
Fill dirt is sold by the cubic yard or by the ton, usually with a minimum load, so get the price both ways and compare them with the density the supplier gives you. A small dump truck often carries around 5 to 7 cubic yards and a larger one 10 to 15, but dirt is heavy enough that the weight limit can cap a load before the bed is full, so ask what one load holds. Every CY Calculator tool shows its working, so you can send the supplier your exact sum with the order.
- Plan the drop spot. A loaded dump truck is heavy and can rut a lawn or crack a thin driveway, so pick firm ground as close to the work as possible.
- Look before it is dumped. Free fill from building sites can hold rocks, roots, broken concrete or debris. Check a load first, and avoid unknown fill anywhere you plan to grow food.
- Call 811 before you dig. In the United States, this free call has underground utility lines marked before any digging starts.
Common Fill Dirt Mistakes
- Measuring the depth in one spot. A single reading on uneven ground can be off by half or more. Average several.
- Forgetting compaction. Fill that is packed down takes up less room, so an exact order comes up short.
- Using topsoil as fill. It costs more and its organic matter breaks down, leaving dips. Use fill dirt underneath and topsoil on top.
- Planting straight into fill dirt. Grass and plants struggle in subsoil. Finish with 4 to 6 inches of topsoil.
- Dumping it all in one go. Spread and compact fill in thin layers, often 4 to 6 inches at a time, so it does not settle unevenly later.
Frequently Asked Questions
How much fill dirt do I need to level my yard?
Multiply the area in square feet by the average depth of the low spots in inches and divide by 324. Raising 1,000 square feet by an average of 2 inches takes 1,000 × 2 ÷ 324 = 6.17 cubic yards. If grass will grow on top, make the last few inches topsoil.
How many yards of dirt are in a dump truck?
It depends on the truck. Smaller dump trucks often carry around 5 to 7 cubic yards and larger ones 10 to 15, but heavy or wet dirt can reach the weight limit first. Ask the supplier how many yards one of their loads holds before you plan the number of trips.
Is fill dirt the same as topsoil?
No. Fill dirt is subsoil with little organic matter, which makes it stable for raising ground but poor for growing. Topsoil is the darker, richer top layer that plants root into. Most projects use fill dirt underneath and a layer of topsoil on top.
How much area does a yard of fill dirt cover?
Divide 324 by the depth in inches. One cubic yard covers 324 ÷ 4 = 81 square feet at 4 inches deep and 324 ÷ 6 = 54 square feet at 6 inches. Compaction makes the finished layer a little thinner than the loose one.
Should fill dirt be compacted?
Yes, wherever anything will sit on it. Spread it in thin layers, water it lightly if it is dry, and compact each layer with a hand tamper or a plate compactor before adding the next. Loose fill left to settle on its own can sink for months.
Is free fill dirt worth it?
It can be for low spots and general grading, as long as you see it first. Free fill often comes from excavation sites and can contain rocks, clay lumps, roots or debris. Use it where those do not matter, and buy screened fill or topsoil for anything you plan to plant.
Final Thoughts
Fill dirt comes down to one sum and two allowances: measure the space, convert to cubic yards, then allow for compaction and for the weight when you plan the hauling. Measure the depth in several places, finish planted areas with topsoil, and check the density with your supplier. For the volume of any shape, use the cubic yard calculator, and for the weight, the Topsoil Calculator works for fill dirt too once you type in your supplier's density.
Put it into practice